Guides · Gantt
Free Power BI Gantt chart with milestones
Use DataLund Gantt when you want tasks, progress, groups, and milestones on one timeline — without a paid visual or a custom Deneb spec.
1. Install the visual
- Download ganttChart.pbiviz (or the full suite zip).
- In Power BI Desktop: Visualizations → … → Import a visual from a file.
- Pick the
.pbivizand add DataLund Gantt to the page.
2. Bind the minimum fields
- Task — work item name
- Start Date
- End Date
3. Mark milestones
A milestone is a zero-duration task: set Start Date and End Date to the same day. DataLund Gantt draws it as a milestone marker on the timeline.
4. Useful format options
- Density — Compact / Comfortable / Large / Custom (Format → General)
- Color by — Default / Resource / Group / Task
- Time window — optional 3 / 6 / 9 / 12 months from today
Next
Add Resource Load for capacity, or build the full project overview with Task List.